Load notes
Substrate Check

A practical site note on load checks for teams who need the right genset size before a shutdown catches production out.
A generator can be sound while the installation around it is not. On South African sites, plinth condition, ventilation, exhaust routing, earthing, and cable paths all affect safe operation. Substrate Check deals with the physical site checks that should happen before problems appear.
Substrate Check starts with the standing area and the actual site load, not the catalogue kVA. On South African plants, cracked concrete, poor drainage, tight cable routes and hot exhaust discharge points can rule out a placement long before the genset arrives. Use the contact form if you need this note tied to a specific shutdown or plant area.
Standing area and load facts
- Peak load and base load listed
- Plinth or slab photos from two angles
- Cable entry route marked from panel
- Site contact and plant role noted
Read this note alongside the unit page that matches the intended duty. Substrate Check covers what the site can physically support, where the cables can run, and how the load behaves during changeover. That information stops a suitable engine from being placed in an unsuitable position.
Checks before a genset lands
A substrate check looks at the site load and the standing area before a genset is selected. Check the actual demand and the installation surface together so the unit size and placement suit the shutdown plan.
Begin at the incomer or main distribution point and confirm what must stay live during an outage. Then inspect the area proposed for the generator, looking at concrete condition, level, anchor points, runoff after rain, and forklift or truck access. In Johannesburg yards this often means dust and hard ground, while Durban sites need closer attention to corrosion, moisture and salt-laden air.
The first photo set should show more than the machine space. Include the panel, the route to the standing area, nearby walls, louvres, drains and any overhead obstructions. Those details affect exhaust direction, cooling airflow and whether cable bends will be too tight for safe installation.
What this note should establish
By the end, the site team should know the likely load band, whether the surface can carry the unit, and what constraints apply to placement. The note should also identify if the job needs civil work, ventilation changes, longer cabling or a revised shutdown sequence. That is more useful than choosing a set only by nameplate size.
Link Substrate Check to the relevant runtime note before finalising placement. If an ATS is part of the shutdown plan, record where it sits, what it feeds, and how far the proposed genset will stand from it.
- Load figure matched to shutdown priority
- Standing area recorded before delivery day
- Panel and site details kept together
Conditions on South African sites
A plant in Ekurhuleni may have heavy vehicle access but limited turning room near the switchroom. A Cape Town site can have stronger wind exposure that affects canopy orientation and exhaust direction. On older industrial properties, earthing points, patched concrete and inherited cable routes often matter as much as the genset rating.
Summer storms expose drainage problems around outdoor installations. Inland dust loads radiators, alternators and panel seals faster, especially where stockyards or crusher areas sit nearby. Coastal humidity can shorten the life of unprotected metalwork, terminals and fasteners if the standing area is not assessed properly at the start.
Operated by Astros Marketing (Pty) Ltd from 2 Makro Place, Sunnyrock 1401.
Records to capture on site
A practical site note on load checks for teams who need the right genset size before a shutdown catches production out.
Write down the measured or estimated load, the dimensions of the proposed area, the surface condition, and the route for power and earth cables. Add notes on noise-sensitive boundaries, exhaust clearance, fuel access and any requirement for temporary barriers during shutdown work. These records help the plant team compare placement options against the actual site rather than assumption.